DETAILS
OF WORKS CONTRACTS PLACED
(For Civil Engg. / Elect. Engg./ S & T/ Mech. etc
works)
(Status : Nov. & Dec. 2006 )
|
S. No. |
Tender No. |
Description of work |
Contract No. and Date |
Contractor’s Name |
Value
( Rs) |
Scheduled date of completion |
Remarks
|
|
A |
From Corporate Office |
|
|
|
|
|
|
1 |
IRCON/CC/TN/Bihar-ROBs/06/256 |
Construction of ROB in Bihar including
sub-structure, super structure, approaches
complete in all respects, at level Xing No. 02
at Gaya. |
IRCON/CC/TN/Bihar-ROBs/06/256/1032 Dated
21.12.2006 |
M/s Prasad Construction & Company,Lila Mohan
Niwas,Naisarai, Biharsarif,Nalanda 803101. |
9,84,71,458.00 |
Nine Months |
|
|
2 |
IRCON/CC/TN/Bihar-ROBs/06/278 |
Construction of ROB in Bihar including
sub-structure, super structure, approaches
complete in all respects, at level Xing No. 02
at Gaya. |
IRCON/CC/TN/Bihar-ROBs/06/278/1036 Dated
27.12.2006 |
M/s Ganesh Yadav,
Anand Nagar, Saraidhella,PO ISM,Dhanbad,
Jharkhand,826001. |
12,65,87,758.00 |
Nine Months |
|
|
B |
From Projects |
|
|
|
|
|
|
|
I |
UPSRP – 01 |
|
|
|
|
|
|
|
1 |
IRCON/1015/UPSRP-01/Tender/C-1/40/125 |
Supply & Transportation of GSB material along
the alignment in Km 42+000 to Km 65+000 in Katra
Bilhaur road for upgradation. |
IRCON/1015/UPSRP-01/Tender/C-1/40/125/2072
Dated 06.11.2006 |
M/s Naresh Kumar |
6,94,40,000.00 |
Seven Months |
|
|
2 |
IRCON/1015/UPSRP-01/Tender/C-1/40/126 |
Supply & Transportation of crushed Aggregate of
various sizes to produce for WMM material at
Allahaganj camp at Project Km 60+000 for
construction of Road works from Km 42+000 to
65+000 of UPSRP-01. |
IRCON/1015/UPSRP-01/Tender/C-1/40/126/2075
Dated 09.11.2006 |
M/s Naresh Kumar |
6,32,05,000.00 |
Seven Months |
|
|
II |
UP- 05 |
|
|
|
|
|
|
|
1 |
IRCON/1020/NHAI
/UP-05/NIT/3
Dated 27.10.2006 |
Supply of Boulders to crusher site of IRCON at
Km 174.500 of NH-25 near Pirauna village, Distt.
Jalaun (UP). |
IRCON/1020/NHAI
/UP-05/NIT/06/
LOA/1152
Dated 11.12.2006 |
M/s CTS Industries Limited, Vishnupuri, Kanpur
|
4,94,00,000.00 |
10.08.07 |
|
|
2 |
IRCON/1020/NHAI
/UP-05/NIT/6
Dated 02.12.2006 |
Earthwork and GSB work Between Km 187+900 to Km
194+400 & Km 196+400 to 201+600 ( Pkg V). |
IRCON/1020/
NHAI/UP-05/
NIT/6/LOA/1147
Dated 30.12.2006 |
M/sTrivedi
Enterprises,
Gaurav
Complex Aurimore,
Sonebhadra. |
6,64,77,128.00 |
31.12.07 |
|
|