1 |
IRCON/1014/J&K. KQ/Bridges/ZoneIIIB/95 dated
04.06.07 |
Construction of Civil Works for Bridge No.119,
121 (balance work) & 122 in Zone IIIB (Km
134-142) on Laole - Quazigund Section of
Udhampur-Srinagar- Baramulla New BG Railway Line
Project |
IRCON/1014/J&K.KQ/ Bridges / Zone IIIB/95/ 1123
dated 23.08.07 |
M/s BUMI
Developers (India) Pvt. Limited |
13,22,86,520/- |
18 months |
Civil
Engg.
J & K:
Laole – Quazigund project |
|
2 |
Ircon /
Electric / 5014 – 15 / 04
|
Supply of
compact secondary Substations |
IRCON/ELEC/5014-5015/04/553,
DT:- 28.08.07 |
M/s
Scheinder Electric Limited. |
9,71,53,661/- |
21 Months |
Elect.
Engg. |
|
3 |
IRCON/
S&T/KASHMIR/6001
/OUTDOOR/04 |
Supply of
outdoor equipment for 10 Stations in Quazigund
Baramulla section |
LOA No.:
IRCON/ S&T/KASHMIR/6001
/OUTDOOR/04
Dated
21.08.2007 |
M/s Alcon
Builders & Engineers Pvt. Ltd., New Delhi |
2,94,70,853/- |
6-months |
S&T
NR's,
Quazigund- Baramulla New B.G. Rail Line
Project's Signaling work |